Beranda

Jumlah OPD 54 Selengkapnya
Jumlah Sub Kegiatan 44/ 1,752 Selengkapnya
Jumlah Paket 55/ 2,461 Selengkapnya
Jumlah Konstruksi 0/ 5 Selengkapnya

Laporan Rekapitulasi Bulanan

1 Januari 2025 sampai dengan 14 Desember 2025

Pekerjaan

Sub Kegiatan Selesai 0% 0/44
Paket Selesai 0% 0/55
Konstruksi Selesai 0% 0/0

Struktur Anggaran (BKPSDM)

BELANJA
Rp15.484.298.500,00 / 86%
Pegawai
Rp1.941.810.000,00 / 91%
Non Pegawai
Rp13.542.488.500,00 / 85%
Barang/Jasa
Rp13.473.605.500,00 / 85%
Modal
Rp68.883.000,00 / 83%

Struktur Sub Kegiatan (BKPSDM)

  • Jumlah 44
  • Selesai 0
  • Tidak Selesai 0
  • Berjalan 40
  • Belum Berjalan 4

Struktur Sumber Anggaran (BKPSDM)

  • APBD
    Rp24.381.803.308,00 / 109%

Laporan Bulanan Fisik (BKPSDM)

Laporan Bulanan Keuangan (BKPSDM)

Rangking Pelaporan OPD

Total 54 hasil
#OPDPagu AnggaranPagu SerapanNilai KontrakRealisasi Progres LaporanJumlah Sub Kegiatan#####Realisasi Laporan Bulan
1KESBANGPOLRp54.149.729.200,00Rp53.230.066.110,00Rp0,0098%313100292Bulan 12
2KECAMATAN KRAMATWATURp6.539.127.385,00Rp6.100.188.132,00Rp0,0093%232380132Bulan 12
3KECAMATAN PETIRRp3.382.931.160,00Rp3.141.132.752,00Rp0,0093%191900163Bulan 12
4KECAMATAN TUNJUNG TEJARp2.986.933.133,00Rp2.732.023.295,00Rp0,0091%16168071Bulan 12
5DISPORAPARRp15.680.470.623,00Rp13.981.796.056,00Rp0,0089%515100474Bulan 12
6KECAMATAN GUNUNG SARIRp3.165.391.238,00Rp2.682.487.315,00Rp0,0085%191900181Bulan 12
7KECAMATAN BOJONEGARARp3.419.175.666,00Rp2.867.964.377,00Rp0,0084%202000173Bulan 12
8DISKOPERINDAGRp18.472.070.721,00Rp15.228.348.394,00Rp0,0082%484800453Bulan 12
9BPBDRp17.124.434.537,00Rp13.799.419.224,00Rp0,0081%343400313Bulan 12
10RSDPRp382.243.812.965,00Rp303.566.432.574,00Rp0,0079%442020Bulan 12
11BAPENDARp63.496.162.195,00Rp46.896.898.783,00Rp0,0074%363600342Bulan 12
12BAPPERIDARp18.369.468.213,00Rp15.772.233.636,00Rp0,0086%666610596Bulan 11
13SETWANRp113.332.140.326,00Rp79.613.091.688,00Rp0,0070%585800499Bulan 11
14DPKDRp21.386.521.679,00Rp13.804.700.049,00Rp0,0065%393939000Bulan 11
15DPMPTSPRp14.445.961.442,00Rp5.488.942.917,00Rp0,0038%363600333Bulan 3
16KECAMATAN CIKANDERp5.131.874.028,00Rp4.541.258.308,00Rp0,0088%191910153Bulan 11
17KECAMATAN PULO AMPELRp3.125.875.634,00Rp2.664.109.055,00Rp0,0085%222200184Bulan 11
18KECAMATAN BAROSRp4.565.082.756,00Rp3.870.190.970,00Rp0,0085%222200220Bulan 11
19DISNAKERTRANSRp10.063.132.077,00Rp8.515.290.151,00Rp0,0085%383800308Bulan 11
20KECAMATAN CARENANGRp2.983.825.864,00Rp2.487.650.763,00Rp0,0083%161600160Bulan 11
21KECAMATAN TIRTAYASARp4.220.042.500,00Rp3.393.854.027,00Rp0,0080%262630212Bulan 11
22BKPSDMRp24.381.803.308,00Rp19.530.052.709,00Rp0,0080%444400404Bulan 11
23KECAMATAN KRAGILANRp4.408.615.176,00Rp3.524.521.234,00Rp0,0080%11110029Bulan 11
24KECAMATAN PABUARANRp4.133.960.301,00Rp3.263.857.544,00Rp0,0079%222200193Bulan 11
25KECAMATAN CIRUASRp5.943.499.476,00Rp4.690.517.731,00Rp0,0079%181811061Bulan 11
26KECAMATAN BINUANGRp3.529.468.586,00Rp2.648.723.621,00Rp0,0075%222200184Bulan 11
27DPMDRp28.032.000.994,00Rp19.802.524.534,00Rp0,0071%393900372Bulan 11
28DISDIKBUDRp1.173.406.449.459,00Rp809.412.515.378,00Rp0,0069%9292008111Bulan 11
29DISHUBRp45.476.563.866,00Rp30.551.069.406,00Rp0,0067%404000400Bulan 11
30KECAMATAN LEBAK WANGIRp3.606.678.242,00Rp2.385.886.336,00Rp0,0066%202000119Bulan 11
31INSPEKTORATRp26.199.552.326,00Rp20.743.310.281,00Rp0,0079%343400268Bulan 8
32DINSOSRp14.794.099.511,00Rp6.139.361.847,00Rp0,0041%4949001831Bulan 7
33DPRKPRp33.368.066.857,00Rp7.292.847.755,00Rp0,0022%383840313Bulan 7
34KECAMATAN CINANGKARp4.892.836.387,00Rp3.898.241.027,00Rp0,0080%191910180Bulan 10
35KECAMATAN BANDUNGRp3.391.962.830,00Rp2.624.546.308,00Rp0,0077%191900190Bulan 10
36KECAMATAN PONTANGRp4.688.905.724,00Rp3.506.651.533,00Rp0,0075%212118021Bulan 10
37SETDARp82.021.106.617,00Rp61.325.120.624,00Rp0,0075%555500550Bulan 10
38DINKESRp342.304.207.030,00Rp228.751.895.450,00Rp0,0067%7171005219Bulan 7
39KECAMATAN CIOMASRp4.045.902.632,00Rp2.922.959.916,00Rp0,0072%151500123Bulan 9
40DISKANRp13.632.380.689,00Rp4.932.810.893,00Rp0,0036%363600324Bulan 7
41DKBPPPARp32.115.137.629,00Rp10.184.935.456,00Rp0,0032%6161004021Bulan 7
42KECAMATAN CIKEUSALRp3.230.227.256,00Rp2.247.904.035,00Rp0,0070%16169061Bulan 6
43KECAMATAN KOPORp3.265.797.795,00Rp1.179.744.879,00Rp0,0036%773013Bulan 6
44KECAMATAN TANARARp4.141.327.512,00Rp1.228.129.044,00Rp0,0030%2121001011Bulan 6
45DPUPRRp158.706.874.013,00Rp32.880.340.866,00Rp0,0021%8080005129Bulan 6
46KECAMATAN KIBINRp4.870.863.301,00Rp547.580.159,00Rp0,0011%330012Bulan 1
47DLHRp38.828.935.248,00Rp27.689.291.793,00Rp0,0071%565620504Bulan 11
48DISKOMINFOSATIKRp20.088.732.108,00Rp12.829.783.542,00Rp0,0064%4545003411Bulan 11
49DISDUKCAPILRp20.582.687.800,00Rp10.305.754.765,00Rp0,0050%2626001214Bulan 7
50DKPPRp33.211.879.772,00Rp11.881.444.931,00Rp0,0036%4747002522Bulan 6
51KECAMATAN WARINGIN KURUNGRp4.494.454.696,00Rp0,00Rp0,000%181800018Belum Berjalan
52BPKADRp701.102.355.756,00Rp0,00Rp0,000%424200042Belum Berjalan
53KECAMATAN JAWILANRp956.600.000,00Rp0,00Rp0,000%110001Belum Berjalan
54KECAMATAN MANCAKRp3.416.342.292,00Rp0,00Rp0,000%212100021Belum Berjalan

Kegiatan Terakhir Ditambah (BKPSDM)

Total 10 hasil
#OPDNama KegiatanPagu Anggaran
1BKPSDMSERTIFIKASI, KELEMBAGAAN, PENGEMBANGAN KOMPETENSI MANAJERIAL DAN FUNGSIONALRp40.000.000,00
2BKPSDMSERTIFIKASI, KELEMBAGAAN, PENGEMBANGAN KOMPETENSI MANAJERIAL DAN FUNGSIONALRp1.380.738.000,00
3BKPSDMSERTIFIKASI, KELEMBAGAAN, PENGEMBANGAN KOMPETENSI MANAJERIAL DAN FUNGSIONALRp754.250.000,00
4BKPSDMSERTIFIKASI, KELEMBAGAAN, PENGEMBANGAN KOMPETENSI MANAJERIAL DAN FUNGSIONALRp270.000.000,00
5BKPSDMPengembangan Kompetensi TeknisRp435.000.000,00
6BKPSDMPENILAIAN DAN EVALUASI KINERJA APARATURRp16.750.000,00
7BKPSDMPENILAIAN DAN EVALUASI KINERJA APARATURRp22.500.000,00
8BKPSDMPENILAIAN DAN EVALUASI KINERJA APARATURRp16.500.000,00
9BKPSDMPENILAIAN DAN EVALUASI KINERJA APARATURRp42.200.000,00
10BKPSDMPENGEMBANGAN KOMPETENSI ASNRp18.500.000,00

Kegiatan Terakhir Diubah (BKPSDM)

Total 10 hasil
#OPDNama KegiatanPagu Anggaran
1BKPSDMADMINISTRASI KEUANGAN PERANGKAT DAERAHRp34.500.000,00
2BKPSDMADMINISTRASI KEUANGAN PERANGKAT DAERAHRp15.486.300.000,00
3BKPSDMPERENCANAAN, PENGANGGARAN, DAN EVALUASI KINERJA PERANGKAT DAERAHRp6.720.000,00
4BKPSDMPERENCANAAN, PENGANGGARAN, DAN EVALUASI KINERJA PERANGKAT DAERAHRp8.529.790,00
5BKPSDMPERENCANAAN, PENGANGGARAN, DAN EVALUASI KINERJA PERANGKAT DAERAHRp17.935.000,00
6BKPSDMSERTIFIKASI, KELEMBAGAAN, PENGEMBANGAN KOMPETENSI MANAJERIAL DAN FUNGSIONALRp1.380.738.000,00
7BKPSDMPENGEMBANGAN KOMPETENSI ASNRp1.185.014.000,00
8BKPSDMMUTASI DAN PROMOSI ASNRp1.723.300.000,00
9BKPSDMPENGADAAN, PEMBERHENTIAN DAN INFORMASI KEPEGAWAIAN ASNRp236.000.000,00
10BKPSDMPENGADAAN, PEMBERHENTIAN DAN INFORMASI KEPEGAWAIAN ASNRp191.614.500,00